2 men and 3 boys can do 3/4 of a piece of work in 6 days; 3 men and 5 boys can do 19/24 of it in 4 days. In what time can a boy do the whole work?

  • A12 days
  • B24 days
  • C36 days
  • D48 days

Correct answer: (D) 48 days

Per day, 2 men + 3 boys do (3/4)/6 = 1/8 of the work, and 3 men + 5 boys do (19/24)/4 = 19/96. Multiplying the first by 3 gives 6m + 9b = 3/8 = 36/96, and the second by 2 gives 6m + 10b = 38/96. Subtracting, one boy does 2/96 = 1/48 of the work per day, so a boy alone takes 48 days.

Try the whole WB Primary TET 2017 paper as a timed test

103 questions, the real time limit, then a full debrief: your rank among PadhoDost students, mistake types and what to fix.

Start the timed test

More Primary TET questions on Mathematics

All Primary TET Mathematics questions, every year →