WB Primary TET · Mathematics · Question 70 of 103

WB Primary TET 2017, Question 112: answer and solution

Source: WBBPE — official question paper (PDF)official answer key (PDF)

Questions: official WBBPE paperAnswers: official keyExplanations: AI-assisted, checked by How we checkReport a mistake

Q112Report

'A' can do a piece of work in 20 days, 'B' can do it in 24 days and 'C' can do the same in 30 days. They agree to do the work in Rs. 5,400 and they start the work together. But 'B' leaves the work before 2 days of the completion of the work and 'C' leaves the work before 5 days of the completion of the work. 'A' completes the remaining work. What amount has 'A' get for the work?

  • ARs. 2,700
  • BRs. 5,400
  • CRs. 1,600
  • DRs. 3,600

Correct answer: (A) Rs. 2,700

Let the work take T days. A works T days, B works T - 2 days and C works T - 5 days, so T/20 + (T - 2)/24 + (T - 5)/30 = 1. Multiplying by 120: 6T + 5T - 10 + 4T - 20 = 120, so T = 10. A does 10/20 = 1/2 of the work, so A gets 1/2 × 5400 = Rs. 2,700.

Try the whole WB Primary TET 2017 paper as a timed test

103 questions, the real time limit, then a full debrief: your rank among PadhoDost students, mistake types and what to fix.

Start the timed test

More Primary TET questions on Mathematics

All Primary TET Mathematics questions, every year →