SSC CGL · Quantitative Aptitude

Time & Work

43 practice questions with full step-by-step solutions, quick revision notes, plus a concept-first explainer — free, no sign-up.

Reviewed by (19 years teaching)Written with AI helpReport a mistake

What you'll learn

The unitary trick: turn 'days' into 'work per day', add them up, and Time & Work becomes easy.

Read Time & Work — Think in '1-Day Work'

This chapter has

11
easy
23
medium
9
hard

Time & Work — quick revision notes

Time and Work covers rates of working, combined work, efficiency, man-days, wages and pipes and cisterns. SSC CGL asks 1-3 questions on it in Tier-I and Tier-II, and most of them can be solved in under a minute with the LCM (total work units) method.
  • If A finishes a job in n days, A does 1/n of it per day. A and B together take (a × b)/(a + b) days: 20 and 30 days together take 600/50 = 12 days.
  • LCM method: take total work = LCM of the given days so that every daily output is a whole number. A = 15 days, B = 20 days → work = 60 units, A = 4 units/day, B = 3 units/day.
  • Efficiency is inversely proportional to time. If A is 50% more efficient than B (efficiency 3 : 2), A takes 2/3 of B's time (time 2 : 3).
  • Chain rule: M1 × D1 × H1 / W1 = M2 × D2 × H2 / W2. 8 men × 15 days × 6 h = 720 man-hours, so 10 men working 8 h a day need 720 ÷ 80 = 9 days.
  • Wages are shared in the ratio of work done, not days taken. If C does 1/8 of the job, C gets 1/8 of the total payment.
  • Pair rates: if (A+B), (B+C) and (C+A) are given, add them to get 2(A+B+C), then halve. 12, 15, 20 days → 5 + 4 + 3 = 12 units = 2(A+B+C), so all three do 6 units/day.
  • Pipes: a filling pipe is positive work, an emptying pipe or leak is negative work. Fill in 10 h, empty in 15 h → net 1/10 − 1/15 = 1/30, so the tank fills in 30 h.
  • Leak shortcut: if a pipe fills a tank in x h alone and in y h with a leak, the leak empties the full tank in xy/(y − x) h. 6 h and 8 h → 48/2 = 24 h.
  • Alternate-day work: find the work done in one full cycle, count the full cycles, then finish the leftover units with whoever works next.

Common mistakes to avoid

  • Adding days instead of rates: 10 days and 15 days together is NOT 25 days; it is 6 days.
  • Splitting wages in the ratio of days taken instead of the ratio of work done (efficiency).
  • In alternate-day questions, forgetting to check whose turn it is on the last, fractional day.
  • Treating a leak or an emptying pipe as positive work.
  • When workers leave or join midway, forgetting to subtract the work already finished before recalculating.
Exam tip: Convert every question to total work units using the LCM of the given days right away; it removes fractions and saves 20-30 seconds per question.

Time & Work — solved practice questions

11 SSC CGL Quantitative Aptitude questions with step-by-step solutions. Attempt each, then reveal the answer.

These worked examples are not in the timed test, so you can study them first.

  1. Q1easyReport

    A can complete a work in 10 days. What part of the work does he do in 1 day?

    • A10
    • B1/5
    • C1/10
    • D1/20
    Show answer & solution

    Correct answer: (C) 1/10

    1 day's work = 1 / (total days) = 1/10.
  2. Q2mediumReport

    A can do a job in 6 days and B in 12 days. Working together, what part do they finish in 1 day?

    • A1/3
    • B1/18
    • C1/4
    • D1/8
    Show answer & solution

    Correct answer: (C) 1/4

    1/6 + 1/12 = 2/12 + 1/12 = 3/12 = 1/4.
  3. Q3mediumReport

    A can do a job in 6 days and B in 12 days. Working together, in how many days will they finish it?

    • A18
    • B8
    • C4
    • D3
    Show answer & solution

    Correct answer: (C) 4

    Together's 1-day work = 1/4, so they finish in 4 days.
  4. Q4mediumReport

    A is twice as efficient as B. If B alone finishes a work in 12 days, how long will A take?

    • A12
    • B8
    • C6
    • D24
    Show answer & solution

    Correct answer: (C) 6

    Twice as efficient → half the time = 12/2 = 6 days.
  5. Q5mediumReport

    4 men build a wall in 10 days. How long will 8 men take, working at the same rate?

    • A2.5
    • B5
    • C20
    • D10
    Show answer & solution

    Correct answer: (B) 5

    Double the men → half the time = 10/2 = 5 days.
  6. Q6hardReport

    A can do a work in 15 days and B in 10 days. What part do they complete together in one day?

    • A1/5
    • B1/6
    • C1/3
    • D1/25
    Show answer & solution

    Correct answer: (B) 1/6

    1/15 + 1/10 = 2/30 + 3/30 = 5/30 = 1/6.
  7. Q7easyReport

    A can do a piece of work in 20 days and B can do it in 30 days. In how many days will they finish it working together?

    • A50 days
    • B10 days
    • C25 days
    • D12 days
    Show answer & solution

    Correct answer: (D) 12 days

    Take total work = LCM(20, 30) = 60 units. A does 60/20 = 3 units/day and B does 60/30 = 2 units/day. Together they do 5 units/day. Time = 60 ÷ 5 = 12 days. (Shortcut: 20 × 30/(20 + 30) = 600/50 = 12 days.)
  8. Q8easyReport

    12 men can complete a work in 18 days. How many men are needed to complete the same work in 8 days?

    • A36
    • B24
    • C27
    • D32
    Show answer & solution

    Correct answer: (C) 27

    Total work = 12 × 18 = 216 man-days. Men needed to finish it in 8 days = 216 ÷ 8 = 27 men.
  9. Q9easyReport

    A and B together can do a work in 8 days. A alone can do it in 12 days. In how many days can B alone do it?

    • A24 days
    • B16 days
    • C4 days
    • D20 days
    Show answer & solution

    Correct answer: (A) 24 days

    B's one-day work = 1/8 − 1/12 = (3 − 2)/24 = 1/24. So B alone takes 24 days. Shortcut: 8 × 12/(12 − 8) = 96/4 = 24 days.
  10. Q10easyReport

    Pipe A can fill a tank in 10 hours and pipe B can empty the full tank in 15 hours. If both pipes are opened together on an empty tank, in how many hours will the tank be filled?

    • A30 hours
    • B6 hours
    • C5 hours
    • D25 hours
    Show answer & solution

    Correct answer: (A) 30 hours

    Take the tank = LCM(10, 15) = 30 units. Pipe A adds 3 units/hour and pipe B removes 2 units/hour. Net filling = 3 − 2 = 1 unit/hour. Time to fill = 30 ÷ 1 = 30 hours.
  11. Q11easyReport

    A is 50% more efficient than B. If B alone can finish a work in 30 days, in how many days can A alone finish it?

    • A45 days
    • B25 days
    • C20 days
    • D15 days
    Show answer & solution

    Correct answer: (C) 20 days

    50% more efficient means efficiency A : B = 150 : 100 = 3 : 2. Time is inversely proportional to efficiency, so time A : B = 2 : 3. B takes 30 days, so 3 parts = 30 and 1 part = 10. A takes 2 × 10 = 20 days.

Ready to test yourself? Take the 32-question Time & Work test →