SSC CGL · Quantitative Aptitude
Time & Work
43 practice questions with full step-by-step solutions, quick revision notes, plus a concept-first explainer — free, no sign-up.
Reviewed by Kaustav Basak (19 years teaching)Written with AI helpReport a mistake
What you'll learn
The unitary trick: turn 'days' into 'work per day', add them up, and Time & Work becomes easy.
Read Time & Work — Think in '1-Day Work'This chapter has
Time & Work — quick revision notes
- If A finishes a job in n days, A does 1/n of it per day. A and B together take (a × b)/(a + b) days: 20 and 30 days together take 600/50 = 12 days.
- LCM method: take total work = LCM of the given days so that every daily output is a whole number. A = 15 days, B = 20 days → work = 60 units, A = 4 units/day, B = 3 units/day.
- Efficiency is inversely proportional to time. If A is 50% more efficient than B (efficiency 3 : 2), A takes 2/3 of B's time (time 2 : 3).
- Chain rule: M1 × D1 × H1 / W1 = M2 × D2 × H2 / W2. 8 men × 15 days × 6 h = 720 man-hours, so 10 men working 8 h a day need 720 ÷ 80 = 9 days.
- Wages are shared in the ratio of work done, not days taken. If C does 1/8 of the job, C gets 1/8 of the total payment.
- Pair rates: if (A+B), (B+C) and (C+A) are given, add them to get 2(A+B+C), then halve. 12, 15, 20 days → 5 + 4 + 3 = 12 units = 2(A+B+C), so all three do 6 units/day.
- Pipes: a filling pipe is positive work, an emptying pipe or leak is negative work. Fill in 10 h, empty in 15 h → net 1/10 − 1/15 = 1/30, so the tank fills in 30 h.
- Leak shortcut: if a pipe fills a tank in x h alone and in y h with a leak, the leak empties the full tank in xy/(y − x) h. 6 h and 8 h → 48/2 = 24 h.
- Alternate-day work: find the work done in one full cycle, count the full cycles, then finish the leftover units with whoever works next.
Common mistakes to avoid
- Adding days instead of rates: 10 days and 15 days together is NOT 25 days; it is 6 days.
- Splitting wages in the ratio of days taken instead of the ratio of work done (efficiency).
- In alternate-day questions, forgetting to check whose turn it is on the last, fractional day.
- Treating a leak or an emptying pipe as positive work.
- When workers leave or join midway, forgetting to subtract the work already finished before recalculating.
Time & Work — solved practice questions
11 SSC CGL Quantitative Aptitude questions with step-by-step solutions. Attempt each, then reveal the answer.
These worked examples are not in the timed test, so you can study them first.
- Q1easyReport
A can complete a work in 10 days. What part of the work does he do in 1 day?
- A10
- B1/5
- C1/10
- D1/20
Show answer & solution
Correct answer: (C) 1/10
1 day's work = 1 / (total days) = 1/10. - Q2mediumReport
A can do a job in 6 days and B in 12 days. Working together, what part do they finish in 1 day?
- A1/3
- B1/18
- C1/4
- D1/8
Show answer & solution
Correct answer: (C) 1/4
1/6 + 1/12 = 2/12 + 1/12 = 3/12 = 1/4. - Q3mediumReport
A can do a job in 6 days and B in 12 days. Working together, in how many days will they finish it?
- A18
- B8
- C4
- D3
Show answer & solution
Correct answer: (C) 4
Together's 1-day work = 1/4, so they finish in 4 days. - Q4mediumReport
A is twice as efficient as B. If B alone finishes a work in 12 days, how long will A take?
- A12
- B8
- C6
- D24
Show answer & solution
Correct answer: (C) 6
Twice as efficient → half the time = 12/2 = 6 days. - Q5mediumReport
4 men build a wall in 10 days. How long will 8 men take, working at the same rate?
- A2.5
- B5
- C20
- D10
Show answer & solution
Correct answer: (B) 5
Double the men → half the time = 10/2 = 5 days. - Q6hardReport
A can do a work in 15 days and B in 10 days. What part do they complete together in one day?
- A1/5
- B1/6
- C1/3
- D1/25
Show answer & solution
Correct answer: (B) 1/6
1/15 + 1/10 = 2/30 + 3/30 = 5/30 = 1/6. - Q7easyReport
A can do a piece of work in 20 days and B can do it in 30 days. In how many days will they finish it working together?
- A50 days
- B10 days
- C25 days
- D12 days
Show answer & solution
Correct answer: (D) 12 days
Take total work = LCM(20, 30) = 60 units. A does 60/20 = 3 units/day and B does 60/30 = 2 units/day. Together they do 5 units/day. Time = 60 ÷ 5 = 12 days. (Shortcut: 20 × 30/(20 + 30) = 600/50 = 12 days.) - Q8easyReport
12 men can complete a work in 18 days. How many men are needed to complete the same work in 8 days?
- A36
- B24
- C27
- D32
Show answer & solution
Correct answer: (C) 27
Total work = 12 × 18 = 216 man-days. Men needed to finish it in 8 days = 216 ÷ 8 = 27 men. - Q9easyReport
A and B together can do a work in 8 days. A alone can do it in 12 days. In how many days can B alone do it?
- A24 days
- B16 days
- C4 days
- D20 days
Show answer & solution
Correct answer: (A) 24 days
B's one-day work = 1/8 − 1/12 = (3 − 2)/24 = 1/24. So B alone takes 24 days. Shortcut: 8 × 12/(12 − 8) = 96/4 = 24 days. - Q10easyReport
Pipe A can fill a tank in 10 hours and pipe B can empty the full tank in 15 hours. If both pipes are opened together on an empty tank, in how many hours will the tank be filled?
- A30 hours
- B6 hours
- C5 hours
- D25 hours
Show answer & solution
Correct answer: (A) 30 hours
Take the tank = LCM(10, 15) = 30 units. Pipe A adds 3 units/hour and pipe B removes 2 units/hour. Net filling = 3 − 2 = 1 unit/hour. Time to fill = 30 ÷ 1 = 30 hours. - Q11easyReport
A is 50% more efficient than B. If B alone can finish a work in 30 days, in how many days can A alone finish it?
- A45 days
- B25 days
- C20 days
- D15 days
Show answer & solution
Correct answer: (C) 20 days
50% more efficient means efficiency A : B = 150 : 100 = 3 : 2. Time is inversely proportional to efficiency, so time A : B = 2 : 3. B takes 30 days, so 3 parts = 30 and 1 part = 10. A takes 2 × 10 = 20 days.
Ready to test yourself? Take the 32-question Time & Work test →