X can do a piece of work in 20 days and Y can do it in 12 days. Y worked at it for 9 days. In how many days can X alone finish the remaining work?

  • A5
  • B3
  • C7
  • D11

Correct answer: (A) 5

Answer by PadhoDost (WBPSC did not publish an answer key for this paper). Y does 1/12 of the work per day, so in 9 days Y does 9/12 = 3/4. The remaining 1/4 is left. X does 1/20 per day, so X needs (1/4) ÷ (1/20) = 5 days.

Try the whole WBPSC Miscellaneous Prelims 2018 paper as a timed test

78 questions, the real time limit, then a full debrief: your rank among PadhoDost students, mistake types and what to fix.

Start the timed test

More WBPSC Misc questions on Mathematics

All WBPSC Misc Mathematics questions, every year →