WBPSC Misc. Services · Mathematics · Question 58 of 76

WBPSC Miscellaneous Prelims 2012 (Session 1), Question 78: answer and solution

Source: WBPSC — official question paper (PDF)no official answer key was published

WBPSC did not publish an answer key for this paper. The answers here are PadhoDost's: each question was solved independently twice and fact-checked, and questions where the checks disagreed are left out.

Questions: official WBPSC paperAnswers: official keyExplanations: AI-assisted, checked by How we checkReport a mistake

A certain work can be done by A and B in 6 days, by B and C in 12 days. If C, alone can do the same work in 36 days then how long will it take to finish the work by working A,B and C together?

  • A5 1/7 days
  • B5 2/7 days
  • C5 3/7 days
  • D5 4/7 days

Correct answer: (A) 5 1/7 days

Answer by PadhoDost (WBPSC did not publish an answer key for this paper). Per day: A + B = 1/6, B + C = 1/12, C = 1/36. So B = 1/12 − 1/36 = 1/18, and A = 1/6 − 1/18 = 1/9. Together = 4/36 + 2/36 + 1/36 = 7/36 of the work per day. Time = 36/7 = 5 1/7 days.

Try the whole WBPSC Miscellaneous Prelims 2012 (Session 1) paper as a timed test

76 questions, the real time limit, then a full debrief: your rank among PadhoDost students, mistake types and what to fix.

Start the timed test

More WBPSC Misc questions on Mathematics

All WBPSC Misc Mathematics questions, every year →