2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then 8 men and 6 boys can do three times the amount of this work in
- A18 days
- B21 days
- C24 days
- D30 days
WBPSC Clerkship · Mathematics · Question 82 of 94
Source: WBPSC — official question paper (PDF)official answer key (PDF)
Questions: official WBPSC paperAnswers: official keyExplanations: AI-assisted, checked by Kaustav BasakHow we checkReport a mistake
2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then 8 men and 6 boys can do three times the amount of this work in